Construction of 1.0 km of a new single carriageway (2 running lanes) with two signalised at grade junctions including underpass structure, constructed immediately adjacent to a live light rail corridor including rail station and secondary school.

  • ESB, NTL and Dublin City Council Water advance diversions
  • Third party consultations – SB School, Veolia (Rail), DCC, DLRCC, local residents
  • Reinforced concrete underpass structure and 2 km boundary retailing wall
  • Phased pedestrian management adjacent to rail station and school
  • Extensive earthworks including deep cuttings in a brown field environment
  • Asbestos removal, soft ground treatment to formation