John Paul Construction

B9016 Keith to Buckie Road Realignment

The works involved the realignment of a narrow single carriageway between Broadley and Clochan junctions over 1 km consisting of both online and offline sections of 6.5 m wide carriageway with 2 no 3.1 m wide running lanes.

  • SSE, BT and Scottish Water advance diversions
  • Third party consultations – SEPA, SNH, Moray Council, local residents
  • Phased TTM design involving multiple traffic switch overs
  • Cut / fill earthworks (20,000 m3)
  • Filter and carrier drainage over 1 km
  • Flexible pavement 7,000 m2 – 60 MSA design with DBM base binder HRA surface course
  • Signing, lining and landscaping